To
attract the private investment to the energy sectors of the African continent, most
of whose power utilities have been publicly owned and hence tariff rate has not
been a big issue, the power purchase agreement is one of the most important factors
to deal with upfront. The faster the countries make their PPA clearer, the
better they get the attention of the investors.
To
attract American private investors in to Africa, the American counterpart
recommended the following what they called important features to include or
consider for a bankable PPA, mainly for renewable energy resources, during US-Africa
Energy Ministerial Conference conducted on June 3-4, 2014 in Addis Ababa,
Ethiopia.
A
bankable power purchase agreement is essentially a long term offtake agreement
executed with a creditworthy offtaker and having a sufficient tenor to enable
repayment of debt by providing an adequate and predicable revenue stream.
1. Dispatch Risk:
There are two structures generally accepted by
lenders for mitigating the risk that the offtaker may not dispatch the
generating facility.
Take or Pay:
The offtaker pays a fixed tariff comprising a
capacity charge (a fixed amount that is paid for available capacity-no dispatch
required) and an output charge (an amount paid in respect of energy actually
delivered). This permits the power producer to cover its fixed costs with the
capacity charge, including the debt service, fixed operating costs, and an
agreed equity return.
Take and Pay
(typical for wind and solar):
The offtaker must take, and pay a fixed tariff for
all energy delivered (no dispatch required).If energy cannot be physically
taken by the offtaker and output is ‘’curtailed,’’ energy will be calculated
and paid for on a deemed delivered basis.
2.
Fixed
Tariff:
It is important that the revenue of any PPA, whether
“take or pay” or “take and pay” be a fixed amount per KWh generated to
adequately cover the cost of operating the facility, repay the debt, and
provide a reasonable return on equity.
3. Foreign Exchange;
In order to avoid subjecting the power producer to
currency risk, the PPA should be either denominated in or linked to an exchange
rate of the currency of the power producer’s debt, and there should be no
limitation or additional approvals required to transfer funds to offshore
accounts as required.
4. Change In Law or Change In Tax;
The agreement should explicitly state which party
takes the risk of the law or tax regime changing after the date of the
agreement in such a way as to diminish the economic returns of the transactions
of such party.(e.g., increase in taxes on power producers reducing the
producer’s returns). In order for PPAs to be bankable, most lenders require the
offtaker to take this risk.
5.
Force
Majeure:
The agreement should excuse the power producer from
performing its obligations if a force majeure event (an event beyond the
reasonable control of such part) prevents such performance. The allocation of
costs and risk of loss associated with a force majeure event will depend on the
availability of insurance and in some cases the degree of political risk in the
country or region.
6. Dispute Resolution:
The agreement should provide for offshore arbitration,
in a neural location, under rules generally acceptable to the international community
(e.g., UNCITRAL, LCIA or ICC).
7. Termination and Termination Payments:
The PPA should set out clearly the basis on which
either part may terminate the PPA. Termination by the off taker may leave the
project with no access to the market and thus should be limited to significant
events. The agreement should provide that if the PPA is terminate by any reason, then in case of transfer of
facility to the off taker, the offtaker shall provide a termination payment at
least equal to the full amount of the power producer’s outstanding bank debt,
and in the case of the offtaker’s default a return on equity.
8.
Assignment:
The PPA should allow collateral assignment of the
agreement to the power producer’s lenders with the right to receive notice of
any default and to cure such default. Additional step-in rights are generally
set forth in a separate direct agreement between the lenders and the off taker.
9. Offtaker payment Support:
Depending upon the size of the project and the
creditworthiness of the offtaker and the development of the energy sector in a
certain country, short term liquidity instrument, a liquidity facility, and/or
a sovereign guaranty will be required to support the offtaker’s payment
obligations.
10. Transmission or Interconnection
Risk:
The
PPA should indicate which party bears the risk of connecting the facility with
the grid and transmitting power to the nearest substation .The more significant
these risks(due to terrain, distance, populated areas), the more the lenders will,
require the offtaker to bear all or significant portion thereof.
Cheers!
Cheers!
No comments:
Post a Comment